| |
FEATURES
of this Power Generation Site:
Notable
features: First commercial Alternating Current 3-phase
hydro power plant
Frequency: 50 cycle
Three-Phase, Alternating Current
Power Transmission Length: 7 miles
Power system built by: General Electric
Notable Engineers: Elihu Thomson,
William Stanley, Almirian
Decker,
Dr. Louis Bell (chief transmission engineer), Edwin
Wilbur Rice Jr., Ernst Danielson
Maximum Power Output: 250 kW
|
Hydro-electric background
Water
power had been used for thousands of years, but use for electricity
began in the mid 19th century. The early power plants like the one
in Dolgeville, NY (1879) ran DC power for industrial uses very close
to the dam. Until the 3-phase AC generator, there was no way to
transmit power long distance (to downtown areas in cities for example).
Redlands,
North Americas First:
The Germans
had proven at the Lauffen-Frankfurt demonstration in 1891
that 3-phase AC power could be sent 109 miles. Westinghouse and
General Electric studied the event and immedicately began working
on 3 phase systems of their own. Elihu Thomson
at General Electric had been working with AC power since 1885, and
set to work on the Redlands plant as a first commercial installation.
The San Bernadino area had already been using DC power to move water
for agriculture and human uses. In 1891 work began to get an AC
power plant in the area to sent power to nearby Redlands, a feat
not possible with the conventional DC power houses.
Why
Redlands?
By the
late 1880's the agricultural business had expanded in southern California.
Valley areas with natural streams were fully utilized by the orange
growers. There was a great quantity of land in the surrounding hills
which could potentially be used for cultivation if there was a way
to pump water uphill. Eastern investors supported the move to build
the Redlands powerhouse which used the power of the Mill Creek.
Pipes were placed under the creekbed to channel almost all the water
into the Pelton waterwheels. The generators are pictured below.
Almirian Decker designed the plant as a whole while Thomson worked
the technical details. Dr. Louis Bell represented the Thomson-Houston
Company(part of General Electric) on the west coast and pioneered
early distance transmission systems. Ernst Danielson, a talented
Swedish engineer helped work on the project and then moved on to
build 3 phase power plants in Sweden. Dr. Louis Bell went on to
work on the Folsom, CA power plant.
If you
wish to read in detail about this plant, please read this
work by Ronald L. Burgess

There were two three-phase hydroelectric generators rated at
250-kw, 2400 volts, each.
The
power was transmitted seven miles to the town of Redlands using
wooden power poles. The year after completion there was a drought.
Today the Mill Creek is mostly piped underground, with a small stream
on the surface (see photo below)
